Building an Extension – Professionals You Need In 10 Easy Steps: Schedule of works or Bill of quantities
Step 5 Schedule of works or bill of quantities
After completing the Design Update We are now ready to start building the tender pack that will go out to the list of contractors, more about the contractors and how to select them in the next stage contractor selection
Schedule of works also abbreviated to SoW
The schedule of works is basically what it says on the tin, an orderly list of the works that will be required to carry out your project.
We put this together in the same logical order that the project will be built, broadly this will be under the following headings
- Site preparation
- Groundworks & drainage
- Floor slab or block and beam
- Brickwork
- Roof structure
- Roof coverings
- Windows
- Plumbing
- Electrical
- Heating
- Carpentry
- Fixtures and fittings (Kitchen for instance)
- Decorations
- Furnishings
- Final clean
A schedule of works does not need to have any meaningful measurements of the works to be priced by the contractor
However must either have a supporting specification or the specific requirements included within the items listed above
Each heading can then be detailed further to allow the contractor to fully understand the work required
Bill of Quantities which is abbreviated to BoQ
The Bill of Quantities is in a similar format and structure as the Schedule of Works
Although produced in NRM format which is the RICS standard for New Rules of Measurement, NRM2 is a set of measurement rules
Defined by Royal Institute of Charted Surveyors The primary purposes of a bill of quantities (BoQ), which becomes a contract document, are:
To provide a coordinated list of items, together with their identifying descriptions and quantities, that comprise the works to enable contractors to prepare tenders efficiently and accurately
The time taken to prepare a BoQ is greater than the Schedule of Works route as all items require measurement or quantification and an extended index of information and documents
In real world scenarios the Bill of Quantities is normally suited to larger projects where the level of detail is in relation to the type and complexity of works.
A Bill of Quantities can provide more certainty to the returned tenders at that time although as the reliance will be on the actual measured works this cost can increase
This consequentially will make the reduction of any works easier to manage and agree upon
Next let’s look at step 6 Contractor selection